The toilet bowl mould. |
The assembled mould. Note the pipe for urine. |
Pouring concrete into the mould. |
The filled toilet bowl mould. |
The mould for the base of the toilet building. |
Leveling the mould. |
The first layer of concrete for the base of the toilet building with the re-bar placed on top. |
The finished base with the walls marked out. |
The first layer of cinder blocks. |
The second layer of cinder blocks. |
The finished wall being prepared for the floor to be poured. Note the two compost compartments. |
The mould, re-bar and drains in place before the floor is poured. |
Starting to pour the floor. |
Pouring the floor. |
The finished floor. Note the protruding re-bar for the walls. |
Laying the first layer of cinder blocks for the steps. |
The first layer of the steps completed. |
Laying the second layer of steps. |
The finished steps. |
The corner posts for the walls. |